ERCOT: the rules for data center loads

Graded Substantial and tightening on how it connects a new large load. 1 states, 6 actions with sources, reviewed 10 October 2026.

Reviewed 10 October 2026 · Part of the Data Center Rulebook

Large-load study paused for a governor-ordered audit until at least December

Substantial↑ Tightening1 states6 items
3in force
2pending
1states
474.0 GWin the queue
5.2xqueue to peak load
Regulation3.8 / 5
  1. Queue process5

    The governor's August 3, 2026 audit directive put Batch Zero and energization of new data center loads on hold until at least December 10, 2026.

  2. Cost allocation3

    SB 6 (June 2025) sets a 75 MW regime of fees and security; the June 2026 full-cost directive awaits legislation per the PUCT's July 17, 2026 reply.

  3. Curtailment4

    SB 6 (June 2025) makes 75 MW loads disclose backup generation and accept mandatory curtailment in grid emergencies, with no penalty terms stated.

  4. On-site generation3

    SB 6 (June 2025) requires review of co-location with existing plants, and the audit directive covers power sourcing for every queued data center.

  5. Available capacity4

    ERCOT's August 2026 notice halts Batch Zero and energization of new large data center loads until the audit ends in mid-December 2026, with 470 GW queued.

Scored on rules in force, 1 to 5. 5 is the most regulated. Pending rules set the arrow.

Interconnection queueSep 2026
474.0 GWrequested
9.5 GWapproved or contracted
4.1 GWenergized
735requests
91.1 GWpeak load
1.9 GW a yearrecent pace
244 yearsof queue at that pace

474 GW tracked as of June 2026 (Senate deck). Batch Zero Sept 2026 classification: 66.4 GW base (204 projects), 127.9 GW studied (158), 302.2 GW excluded (373). Approved to energize 9,456 MW; ~4.1 GW operational Sept 2026. Audit due Dec 10, 2026. ERCOT preliminary long-term load forecast (Apr 15, 2026) projects ~367,790 MW of demand in the ERCOT region by 2032 vs 85,508 MW all-time peak; ERCOT cautions it may be inflated ercot.com Pace: Growth in large load with ERCOT Approval to Energize, 6,874 MW (May 2025) to 9,456 MW (Sep 2026), about 1,940 MW a year; Jan to Sep 2026 alone ran at about 890 MW a year under the August 2026 approvals pause ercot.com

  • ERCOT Senate Committee briefing (June 2026 figures) ~474 GW of large loads seeking interconnection, ~90% data centers; ~205 GW preliminarily eligible for Batch Zero as of July 28, 2026 Jul 2026 ercot.com
  • ERCOT Monthly Operational Overview (September 2026) 9,456 MW approved to energize; 4,132 MW non-simultaneous peak consumption observed Sept 2026 (operational approved load) Sep 2026 ercot.com
  • ERCOT LLWG (March 2026, via ZeroEmissionGrid summary) Queue ~238 GW plus 137 new requests (~140 GW) = ~380 GW; only ~2,168 MW approved to energize and ~5,878 MW planning studies approved in prior 12 months Mar 2026 zeroemissiongrid.com
  • Governor Abbott audit (Utility Dive) ~474 GW queue, ~90% data centers; approvals to energize paused for 75 MW+ data centers and crypto from Aug 3, 2026; ~300 data centers (~49.8 GW) under audit Aug 2026 utilitydive.com

ERCOT has about 474 GW of large-load requests, roughly 90 percent of them data centers and more than five times its record peak. Senate Bill 6 of 2025 set a 75 MW threshold with disclosure and emergency curtailment duties, and ERCOT built a one-time batch study, Batch Zero, to sort the queue. On 3 August 2026 the governor ordered an audit of every data center in the queue, and ERCOT paused the study and the energization of new data center and crypto loads until it is done.

Outlook for the next year

ERCOT's verification and community impact reports are due to the Public Utility Commission by 10 December 2026, with final Batch Zero classifications expected that month and the April 2027 study date in doubt. The Legislature convenes in January 2027 and the commission is expected to ask for more authority over data centers.

How does ERCOT treat a new data center load?

ERCOT is graded Substantial and tightening on how it connects a new large load: Large-load study paused for a governor-ordered audit until at least December ERCOT has about 474 GW of large-load requests, roughly 90 percent of them data centers and more than five times its record peak. Senate Bill 6 of 2025 set a 75 MW threshold with disclosure and emergency curtailment duties, and ERCOT built a one-time batch study, Batch Zero, to sort the queue. On 3 August 2026 the governor ordered an audit of every data center in the queue, and ERCOT paused the study and the energization of new data center and crypto loads until it is done.

How much load is waiting to connect in ERCOT?

474.0 GW of large-load interconnection requests as of Sep 2026, of which 9.5 GW approved or contracted and 4.1 GW energized. 474 GW tracked as of June 2026 (Senate deck). Batch Zero Sept 2026 classification: 66.4 GW base (204 projects), 127.9 GW studied (158), 302.2 GW excluded (373). Approved to energize 9,456 MW; ~4.1 GW operational Sept 2026. Audit due Dec 10, 2026. At the recent pace of about 1.9 GW a year (Growth in large load with ERCOT Approval to Energize, 6,874 MW (May 2025) to 9,456 MW (Sep 2026), about 1,940 MW a year; Jan to Sep 2026 alone ran at about 890 MW a year under the August 2026 approvals pause), the queue represents roughly 244 years of connections, which is why most of it will never be built.

Which states are in ERCOT?

Texas. Each state page gives that state's own laws, incentives and local actions, which sit under the grid's connection rules.

Which states in ERCOT are tightening their data center rules?

1 of 1: Texas.

What is the outlook for data centers in ERCOT?

ERCOT's verification and community impact reports are due to the Public Utility Commission by 10 December 2026, with final Batch Zero classifications expected that month and the April 2027 study date in doubt. The Legislature convenes in January 2027 and the commission is expected to ask for more authority over data centers.

Every item, newest first

6 items: each is a law, order, tariff, ruling, utility action or local decision that changes what a data center must do, pay or disclose, or where it may be built. Failed and pending measures are marked. Each links to its source.

  1. Grid operatorSep 2026grid connectionIn force

    Audit timetable and further information requests

    ERCOT said in early September 2026 that it intends to finish the data center audit by 10 December 2026 and will send a report to the Public Utility Commission a week before that month's open meeting. First information requests went out in late August and early September, and ERCOT said more rounds may follow in October and November. About 300 planned data centers are covered. Batch Zero and new large-load connections stay on hold until the audit is done.

    Source: datacenterdynamics.com
  2. Grid operatorSep 2026grid connectionPending

    Batch Zero status after the pause

    As of ERCOT's mid-September 2026 board update, 362 large loads were provisionally in the study: 204 base-case projects of 66.4 GW and 158 studied projects of about 125 GW, with 373 projects of 302 GW excluded. Final classification moved from 7 August to December 2026, the effect on the 9 April 2027 study deadline is undetermined, and energization of new large data center and crypto loads is paused until the audit and community impact review finish.

    Source: ercot.com
  3. Grid operatorAug 2026grid connectionIn force

    Governor's audit directive for data centers in the ERCOT queue

    The 3 August 2026 letter requires verification of all data centers in the interconnection process before any more advance, covering incentives, power sourcing, water, community impact and ownership; projects found in violation are to be denied connection and loads that do not respond are classed ineligible. ERCOT is sending mandatory information requests to Batch Zero loads and to about 8,766 MW of loads between 25 and 75 MW. ERCOT asked the Public Utility Commission for deadline waivers on 10 August, and its long-term load forecast is delayed.

    Source: gibsondunn.com
  4. Grid operatorJul 2026costs and tariffsPending

    Direction that data centers pay full infrastructure cost

    In June 2026 the governor directed that data centers bear the full cost of the lines, substations and upgrades built for them. The Public Utility Commission chair replied on 17 July 2026 that the commission had acted within its existing authority but that comprehensive regulation needs new legislation.

    Source: troutman.com
  5. Grid operatorJan 2026reliabilityExpired

    Department of Energy emergency order for ERCOT

    Order 202-26-01 of 24 January 2026 authorized ERCOT to direct backup generation at data centers and other large sites to run as a last resort before load shedding during the winter storm, through 27 January.

    Source: energy.gov
  6. Grid operatorJun 2025grid connectionIn force

    Senate Bill 6 large-load law

    Signed in June 2025. Loads of 75 MW or more must disclose on-site backup generation to ERCOT and can be curtailed in grid emergencies. ERCOT's Batch Zero study applies the same 75 MW threshold.

    Source: troutman.com