Data center regulations in Florida

Graded Substantial and tightening. 14 laws, orders, rulings and local actions, each with its source, reviewed 23 October 2026.

Reviewed 23 October 2026 · Part of the Data Center Rulebook

2026 law makes 50 MW loads pay full cost; counties pause

Substantial↑ TighteningGrid: Southeast utilities14 items
9in force
5pending
3local pauses
narrowedtax break
3.3combined index (5 most)
8.9cper kWh, industrial
23 October 2026reviewed
Regulation3.6 / 5
  1. Grid connection3

    SB 484 (1 July 2026) bars tariffs that block curtailment, and FPL's Nov 2025 terms make 50 MW loads fund a study, a substation and 100% of new generation.

  2. Power rates5

    SB 484, in force 1 July 2026, is a statewide full cost-of-service law for 50 MW loads; FPL's compliant tariff adds 20-year terms, minimum bills and exit fees.

  3. Siting and land use3

    Palm Beach (24 Sept 2026), Sarasota and Nassau county pauses and a dozen more county restrictions reach a main market; Miami-Dade, Tampa and Orlando stay open.

  4. Tax treatment3

    HB 7031, effective 1 Aug 2025, narrowed the sales tax exemption to facilities of 100 MW or more with no grandfathering; it runs to June 2037.

  5. Permits and water4

    SB 484's water rules (2026) deny permits that harm water resources, require reclaimed water and force a hearing above 100,000 gallons a day.

Scored on rules in force, 1 to 5. 5 is the most regulated. Pending rules set the arrow.

Florida enacted SB 484 in May 2026. It requires the Public Service Commission to make customers of 50 MW or more bear their full cost of service, protects local zoning authority, cuts data center projects out of the 12-month confidentiality extension for economic development records and tightens water permitting. The four investor-owned utilities filed tariffs or compliance statements by 1 October 2026; FPL says its 20-year large-load tariff approved in November 2025 already complies. The sales tax exemption survives through June 2037 but since August 2025 only for facilities of 100 MW or more. More than a dozen counties have adopted moratoria or bans, including 12-month pauses in Nassau, Sarasota and Palm Beach, and Manatee County is drafting one.

Outlook for the next year

The PSC must now review the 1 October 2026 filings: FPL's compliance statement, Tampa Electric's new tariff, with a decision expected in late 2026 or early 2027, and Duke Energy Florida's proposed 20-year large-load tariff in Docket 20260064-EI, where Duke commits to a dedicated rate effective 1 January 2028. The act sets no PSC rulemaking deadline. A state-commissioned study of data center impacts is due 1 July 2027. Manatee County's moratorium still needs planning commission and board hearings, and the Fort Meade development agreement has not been confirmed. The 3 November 2026 governor's race matters: Democrat David Jolly has pledged a first-day moratorium on hyperscale data centers and said in September that a complete ban should be on the table, while Republican Byron Donalds favors local siting control with ratepayer protections.

Does Florida have a data center moratorium in force?

No statewide moratorium, but 3 local pauses are in force as of 23 October 2026, in Nassau County, Palm Beach County, Sarasota County. Proposals and expired pauses are not counted.

Is Florida tightening or loosening its rules on data centers?

Tightening. Florida is graded Substantial, which means binding new costs, siting limits or disclosure rules on new data centers. 2026 law makes 50 MW loads pay full cost; counties pause. The outlook above says what is pending.

Which grid operator covers Florida?

Florida sits in Southeast utilities. The grid operator decides how a new large load is studied, what it must bring or pay, and whether it can be curtailed first; the state decides siting, permits, tariffs and incentives.

Has Florida cut its data center tax incentive?

Yes. Florida has paused, narrowed or ended a data center incentive in 2025 or 2026: HB 7031: sales tax exemption limited to 100 MW and above.

How regulated are data centers in Florida?

On Genloop's five-line rubric (1 least regulated, 5 most) Florida scores grid connection 3, power rates 5, siting and land use 3, tax treatment 3, permits and water 4, a mean of 3.6. The most regulated line is power rates: SB 484, in force 1 July 2026, is a statewide full cost-of-service law for 50 MW loads; FPL's compliant tariff adds 20-year terms, minimum bills and exit fees.

Every item, newest first

14 items: each is a law, order, tariff, ruling, utility action or local decision that changes what a data center must do, pay or disclose, or where it may be built. Failed and pending measures are marked. Each links to its source.

  1. UtilityFlorida Power & LightOct 2026costs and tariffsIn force

    FPL tells PSC its large-load tariff already complies with SB 484

    FPL's Large Load Contract Service terms, approved in November 2025 as part of its 2026 to 2029 rate plan, require applicants to fund an engineering study, pay 100 percent of new generation built for them, build their own substation, meet a minimum bill on reserved capacity, sign a 20-year minimum contract and pay an exit fee. The PSC still has to review the compliance filing.

    Source: wusf.org
  2. UtilityTampa ElectricOct 2026costs and tariffsPending

    Tampa Electric large-load tariff filing

    Filed with the PSC under SB 484. Large-load customers would pay for the infrastructure that serves them and a share of system costs. TECO has no such customer yet and expects a decision in late 2026 or early 2027.

    Source: baynews9.com
  3. RegulatorOct 2026costs and tariffsPending

    PSC implementation of SB 484

    Each investor-owned utility (FPL, Duke Energy Florida, Tampa Electric and Florida Public Utilities) had to file a tariff complying with s. 366.043 for PSC approval by 1 October 2026. The PSC may approve tools such as minimum bills, exit fees and credit support but the act sets no rulemaking deadline. Municipal utilities and cooperatives such as JEA, OUC and Gainesville Regional Utilities are not covered.

    Source: flsenate.gov
  4. LocalPalm Beach CountySep 2026moratoriaIn force

    Palm Beach County one-year moratorium on data centers of 50 MW or more

    Commissioners voted 6-0 on 24 September 2026 to stop accepting or approving zoning requests for data centers with peak load of 50 MW or more in unincorporated areas for up to a year. In July they rejected a large expansion of Project Tango, which keeps a smaller 2016 approval.

    Source: cbs12.com
  5. LocalSarasota CountyJul 2026moratoriaIn force

    Sarasota County 12-month moratorium

    Sarasota County adopted a 12-month pause on data centers in July 2026 to study impacts and write permanent rules.

    Source: baynews9.com
  6. RegulatorDuke Energy FloridaJul 2026costs and tariffsPending

    Duke Energy Florida large-load tariff (Docket 20260064-EI)

    Proposed for customers expected to reach 50 MW or more: a 20-year contract, minimum payments on 75 to 85 percent of contracted capacity, credit support, two years' notice to leave and an exit payment of three years of minimum bills plus unrecovered facility costs. The case was at the prehearing stage in late July 2026.

    Source: psc.state.fl.us
  7. LocalManatee CountyJul 2026moratoriaProposed

    Manatee County begins moratorium process

    Commissioners voted unanimously in late July 2026 to have staff draft a moratorium on data centers and similar large-load projects, intended to last at least a year, along with new development rules on power, water and public safety. It still needs hearings before the planning commission and the board; final adoption was not confirmed. The report says more than a dozen Florida counties have adopted moratoria or bans.

    Source: govtech.com
  8. LocalNassau CountyJun 2026moratoriaIn force

    Nassau County 12-month moratorium

    Commissioners approved a 12-month moratorium in June 2026 on accepting, reviewing or approving data center applications, including rezonings and site plans, while a committee studies impacts.

    Source: news4jax.com
  9. State lawMay 2026costs and tariffsIn force

    SB 484 (Chapter 2026-65): full cost of service for loads of 50 MW or more

    Signed 7 May 2026 after votes of 31-6 and 92-16; most provisions took effect 1 July 2026. Customers with an anticipated monthly peak of 50 MW or more at one site must bear their full cost of service and may not split loads to avoid it. Tariffs may not block curtailment for grid stability, and utilities may not knowingly serve large loads controlled by foreign countries of concern.

    Source: flsenate.gov
  10. State lawMay 2026siting and zoningIn force

    SB 484: local control and shorter confidentiality for data center deals

    Local governments keep comprehensive planning and land development authority over large-load customers, and a large load customer may not be treated as an electric substation under s. 163.3208; these provisions took effect on signing, 7 May 2026. The act also bars data center projects from the 12-month extension of confidentiality for economic development information under s. 288.075, so project details become public sooner.

    Source: flsenate.gov
  11. State lawMay 2026waterIn force

    SB 484: water permitting for large-scale data centers

    Water permits may not be issued if the use would harm water resources or conflict with local zoning. Reclaimed water must be used where available and feasible, and applications averaging 100,000 gallons a day or more need detailed source and conservation plans and a hearing.

    Source: news4jax.com
  12. LocalFort Meade (Polk County)Apr 2026siting and zoningApproved, not yet effective

    Fort Meade data center plan advances

    Fort Meade's planning board approved Stonebridge's plan for 1.9 million square feet, expandable to 4.4 million, on 7 April 2026 despite a petition of about 500 residents. By July 2026 the city was reported to have agreed to a development plan.

    Source: baynews9.com
  13. LocalSt. Lucie CountyOct 2025siting and zoningPending

    Sentinel Grove Technology Park (Project Jarvis)

    The county planning and zoning commission voted 4-2 in October 2025 to recommend against a plan amendment for a 1,218-acre campus near Fort Pierce planned for a first 1,000 MW. In February 2026 a county commissioner said the developer appeared to have pulled back ahead of the state data center law, though it had not formally withdrawn. No county commission vote has been reported.

    Source: wflx.com
  14. State lawAug 2025incentivesIn force

    HB 7031: sales tax exemption limited to 100 MW and above

    Passed 30 June 2025 and effective 1 August 2025. The data center sales tax exemption now applies only to facilities with a critical IT load of 100 MW or more, up from 15 MW, with no grandfathering for smaller sites.

    Source: ryan.com