NYISO: the rules for data center loads

Graded Light and tightening on how it connects a new large load. 1 states, 4 actions with sources, reviewed 10 October 2026.

Reviewed 10 October 2026 · Part of the Data Center Rulebook

Tariff found inadequate; reliability gap forecast from 2031 in New York City

Light↑ Tightening1 states4 items
0in force
3pending
1states
12.0 GWin the queue
0.4xqueue to peak load
Regulation2.0 / 5
  1. Queue process2

    Loads above 10 MW at 115 kV already go through NYISO study, but FERC found June 18, 2026 there is no large-load definition or standard procedure.

  2. Cost allocation1

    No collateral, minimum term or capacity charge for large loads is in force; the seasonal capacity market comes in 2027.

  3. Curtailment1

    No curtailment or capacity-matching obligation is in force; assigning resource deficiencies to large loads is a March 2027 proposal.

  4. On-site generation3

    FERC's June 18, 2026 order found no co-location rules, so co-location proceeds under review pending NYISO's November 2026 response.

  5. Available capacity3

    NYISO's 2026 Q2 STAR confirms a 184 to 201 MW Lower Hudson Valley deficiency from 2029, driven by New York City and Long Island; solutions sought Aug 20, 2026.

Scored on rules in force, 1 to 5. 5 is the most regulated. Pending rules set the arrow.

Interconnection queueMar 2026
12.0 GWrequested
500 MWenergized
48requests
31.9 GWpeak load

48 large load proposals totaling about 12 GW in the NYISO queue as of Dec 31 2025 (6 projects, 1 GW in 2022); over 8 GW entered in 2025 alone; NYISO says it cannot predict how many get built. NYISO 2026 RNA assumes 1,211 to 4,113 MW of large load demand by 2036 (2025 page said 2,500 to 4,000 MW by 2035) nysrc.org Pace: Not found. NYISO 2026 ICAP peak load forecast carries 538 MW of large load for summer 2026 (National Grid 306, NYPA 160, O&R 72) as forecast, not energized; Gold Book update and queue pages give queue (11.9 GW) only.

  • NY PSC (Case 26-E-0045) 11.9 GW of prospective large load in the NYISO queue as of Feb 2026; more than 8.3 GW entered in 2025 Feb 2026 rtoinsider.com
  • NYISO MMU State of the Market over 12 GW of large load projects in the queue as of March 2026; about 500 MW of large loads (mostly crypto) entered service in the past decade; most queued loads do not plan onsite generation or flexible operation Mar 2026 nysrc.org
  • NYISO (prior figure) 29 large load projects, nearly 6,055 MW, as of July 2025 Jul 2025 nyiso.com

FERC found in June 2026 that NYISO's load connection procedures are only partly in its tariff and lack rules for large-load studies, cost responsibility, co-location and flexible service. NYISO's own preliminary 2026 assessment shows a possible statewide reliability violation from 2033 and New York City needs as early as 2031. It is considering making large loads responsible for the resource shortfalls they cause. State permitting limits on large data centers are a separate matter covered under New York.

Outlook for the next year

NYISO's response on large-load connection is due from mid-November 2026, and a separate filing on resource adequacy responsibility is targeted for about March 2027. The capacity market moves to a seasonal design in 2027.

How does NYISO treat a new data center load?

NYISO is graded Light and tightening on how it connects a new large load: Tariff found inadequate; reliability gap forecast from 2031 in New York City FERC found in June 2026 that NYISO's load connection procedures are only partly in its tariff and lack rules for large-load studies, cost responsibility, co-location and flexible service. NYISO's own preliminary 2026 assessment shows a possible statewide reliability violation from 2033 and New York City needs as early as 2031. It is considering making large loads responsible for the resource shortfalls they cause. State permitting limits on large data centers are a separate matter covered under New York.

How much load is waiting to connect in NYISO?

12.0 GW of large-load interconnection requests as of Mar 2026 and 500 MW energized. 48 large load proposals totaling about 12 GW in the NYISO queue as of Dec 31 2025 (6 projects, 1 GW in 2022); over 8 GW entered in 2025 alone; NYISO says it cannot predict how many get built.

Which states are in NYISO?

New York. Each state page gives that state's own laws, incentives and local actions, which sit under the grid's connection rules.

Which states in NYISO are tightening their data center rules?

1 of 1: New York.

What is the outlook for data centers in NYISO?

NYISO's response on large-load connection is due from mid-November 2026, and a separate filing on resource adequacy responsibility is targeted for about March 2027. The capacity market moves to a seasonal design in 2027.

Every item, newest first

4 items: each is a law, order, tariff, ruling, utility action or local decision that changes what a data center must do, pay or disclose, or where it may be built. Failed and pending measures are marked. Each links to its source.

  1. Grid operatorJul 2026reliabilityProposed

    Resource adequacy plan for large loads

    In its July 2026 report to FERC, NYISO said its preliminary 2026 Reliability Needs Assessment shows a possible statewide deficiency of more than 1,800 MW from 2033 and New York City needs as early as 2031. It is considering assigning responsibility for resource deficiencies to the large loads that cause them and a faster study path for resources that meet a reliability need, with a tariff filing around March 2027.

    Source: climatesolutionslaw.com
  2. Grid operatorJul 2026costs and tariffsPending

    Capacity market changes

    NYISO told FERC it will move to a seasonal capacity market in 2027, is changing accreditation to reflect fuel constraints in 2026, and is revising how it resets capacity demand curves.

    Source: climatesolutionslaw.com
  3. Grid operatorJun 2026grid connectionPending

    FERC large-load show-cause order (EL26-69)

    The 18 June 2026 order found four gaps: no adequate definition of a large load, unclear application and study procedures, thin operating requirements and no standard service agreement. Today loads above 10 MW at 115 kV or higher, or 80 MW and up at lower voltage, go through NYISO study. FERC said studies should take no more than 60 to 90 days.

    Source: akingump.com
  4. Grid operatorJan 2026reliabilityExpired

    Department of Energy emergency order for NYISO

    Order 202-26-08 of 26 January 2026 directed all units to run at maximum output through 2 February during the winter storm.

    Source: energy.gov