SPP: the rules for data center loads

Graded Moderate and steady on how it connects a new large load. 15 states, 5 actions with sources, reviewed 10 October 2026.

Reviewed 10 October 2026 · Part of the Data Center Rulebook

Most complete large-load toolkit of any grid operator, already in force

Moderate→ Steady15 states5 items
3in force
1pending
15states
30.0 GWin the queue
0.5xqueue to peak load
Regulation2.6 / 5
  1. Queue process3

    The HILL process, FERC-approved January 14, 2026, is a formal study for loads of 50 MW or more with forecast, disconnect and ride-through requirements.

  2. Cost allocation2

    The HILL rules (January 2026) impose equipment and forecast duties but no collateral or minimum term is described in the file.

  3. Curtailment3

    CHILLS (effective July 1, 2026) lets a load connect early on curtailable service, and HILL loads must have remote disconnect capability.

  4. On-site generation2

    The HILLGA study (January 2026) gives paired generation within two substations a defined 150-day review, so co-location is allowed and relatively simple.

  5. Available capacity3

    SPP's July 20, 2026 report shows a 7.06 percent summer 2026 accredited reserve margin; loads connect early only on curtailable CHILLS service (July 1, 2026).

Scored on rules in force, 1 to 5. 5 is the most regulated. Pending rules set the arrow.

Interconnection queueMar 2026
30.0 GWrequested
7.0 GWapproved or contracted
58.0 GWpeak load

SPP publishes no running HILL queue total. Stakeholders submitted ~30 GW of new large loads for the 2026 ITP (11 GW in 2025 ITP); cumulative 100 MW+ requests since 2020 ~26.4 GW with ~7 GW in executed service agreements. HILL process FERC-approved Jan 2026. SPP 2026 ITP futures: peak 91 GW (Future 1) to 110 GW (Future 2) by 2035 vs 56 GW record peak (Aug 2023); SPP Oct 2025 slide shows 75 GW base and 105 GW including spot loads modoenergy.com Pace: Not found. SPP Aug 2026 status update to MO PSC gives HILL requests (11 requests, 3,871 MW; 568 MW added to service agreements) and no energized figure; SPP blog and Modo give pipeline only.

  • SPP large load requests (CES byline citing SPP) ~26.4 GW of 100 MW+ load interconnection requests since 2020 incl. 9 GW data centers; ~6 GW received in 2024 alone; only ~7 GW reached executed service agreements (service dates 2021-2027) Apr 2026 ces-ltd.com
  • SPP to Missouri PSC reliability panel SPP peak today 56 GW; latest 2026 ITP 75 GW; 2026 ITP forecast including spot loads 105 GW; HILL approved by Board Sept 4, 2025 Oct 2025 psc.mo.gov
  • Evergy (Kansas/Missouri) ~2.5 GW signed ESAs across five data center projects (~3 GW incl. other large customers; 1.3 GW operating or near steady state, 1.7 GW under contract); 2 to 2.5 GW expansion plus 1 to 2 GW Tier 2 in advanced talks; remaining pipeline over 10 GW Aug 2026 marketbeat.com
  • FERC order on SPP HILL (Troutman) SPP told FERC nearly 6 GW of HILLs requested interconnection in 2024; HILL effective Jan 15, 2026 (Docket ER26-247) Jan 2026 troutmanenergyreport.com

SPP is the only grid operator with FERC-approved large-load rules already operating: a defined study process for loads of 50 MW or more, a 150-day study for generation built next to them, and a curtailable service that lets a load connect before firm upgrades are finished. FERC used SPP's 50 MW definition as the model for its national show-cause orders. SPP has told FERC its existing framework largely answers the order. The summer of 2026 still brought federal emergency orders for the region.

Outlook for the next year

SPP plans to file a price-responsive load product on or before 16 November 2026 and is refining curtailment rules for its interim service. FERC must still decide whether SPP's existing rules satisfy the show-cause order.

How does SPP treat a new data center load?

SPP is graded Moderate and steady on how it connects a new large load: Most complete large-load toolkit of any grid operator, already in force SPP is the only grid operator with FERC-approved large-load rules already operating: a defined study process for loads of 50 MW or more, a 150-day study for generation built next to them, and a curtailable service that lets a load connect before firm upgrades are finished. FERC used SPP's 50 MW definition as the model for its national show-cause orders. SPP has told FERC its existing framework largely answers the order. The summer of 2026 still brought federal emergency orders for the region.

How much load is waiting to connect in SPP?

30.0 GW of large-load interconnection requests as of Mar 2026, of which 7.0 GW approved or contracted. SPP publishes no running HILL queue total. Stakeholders submitted ~30 GW of new large loads for the 2026 ITP (11 GW in 2025 ITP); cumulative 100 MW+ requests since 2020 ~26.4 GW with ~7 GW in executed service agreements. HILL process FERC-approved Jan 2026.

Which states are in SPP?

Arkansas, Colorado, Iowa, Kansas, Louisiana, Minnesota, Missouri, Montana, Nebraska, New Mexico, North Dakota, Oklahoma, South Dakota, Texas and Wyoming. Each state page gives that state's own laws, incentives and local actions, which sit under the grid's connection rules.

Which states in SPP are tightening their data center rules?

12 of 15: Arkansas, Colorado, Iowa, Kansas, Minnesota, Missouri, Montana, Nebraska, New Mexico, North Dakota, Oklahoma, Texas.

What is the outlook for data centers in SPP?

SPP plans to file a price-responsive load product on or before 16 November 2026 and is refining curtailment rules for its interim service. FERC must still decide whether SPP's existing rules satisfy the show-cause order.

Every item, newest first

5 items: each is a law, order, tariff, ruling, utility action or local decision that changes what a data center must do, pay or disclose, or where it may be built. Failed and pending measures are marked. Each links to its source.

  1. Grid operatorAug 2026reliabilityExpired

    Department of Energy emergency orders for SPP

    Orders 202-26-36 and 202-26-37 (20 July to 10 August 2026) authorized SPP to dispatch units beyond normal limits and call on backup generation as a last resort during summer heat.

    Source: energy.gov
  2. Grid operatorJul 2026grid connectionIn force

    Conditional High Impact Large Load Service (CHILLS)

    Effective 1 July 2026. A large load can take curtailable transmission service and connect on available capacity while firm upgrades are built. Refinements to commitment sequencing and curtailment ramp rates are in development.

    Source: climatesolutionslaw.com
  3. Grid operatorJul 2026grid connectionPending

    FERC large-load show-cause order (EL26-68)

    SPP told FERC in July 2026 that its existing framework already covers large-load resource adequacy and that no immediate overhaul is needed. It is developing a Price Adaptive Load product with a FERC filing targeted on or before 16 November 2026.

    Source: climatesolutionslaw.com
  4. Grid operatorJan 2026grid connectionIn force

    High Impact Large Load (HILL) process and paired-generation study (HILLGA)

    FERC approved both on 14 January 2026, effective the next day. A HILL is a new or expanded load of 50 MW or more above 69 kV, or 10 MW or more at 69 kV or below; it must provide added forecasts, remote disconnect capability, phasor measurement units and ride-through. The optional HILLGA study takes 150 days for generation within two substations of the load, which must be in commercial operation within five years.

    Source: wrightlaw.com
  5. Grid operatorJul 2025grid connectionIn force

    Expedited Resource Adequacy Study (ERAS)

    A one-time fast track for new generation that utilities need for reliability, approved by FERC in July 2025. As of July 2026 it held 36 active requests totaling about 13.3 GW, with interconnection agreements expected to be signed in September 2026.

    Source: climatesolutionslaw.com