Read that again from the engineering side. A boiler and a steam turbine is 1920s thermodynamics. It burns gas to make steam to spin a shaft, and on the EIA's 2025 figures it needs about 10,300 Btu of fuel for every kilowatt hour, barely better than a simple-cycle gas turbine and far worse than a modern combined-cycle plant. One of the most sophisticated compute operators in the country chose it anyway, because it was the one large block of firm generation he could buy with a delivery date inside the decade.
That is the story the industry has been telling since the summer: the gas turbine is sold out, so developers are going old school. It is the right observation and the wrong lesson. The lesson is not that boilers are back. It is that the steam side of the supply chain is open while the gas side is shut, and that every simple-cycle campus being built right now, from Abilene to Amarillo, is throwing away the heat that a steam turbine would turn into power. The cheapest megawatts in America are the ones somebody already paid for and is venting into the sky.
Quick takeaways
- A large gas turbine ordered today ships around 2031, by GE Vernova's and Mitsubishi Power's own account, and GE Vernova is reserving slots into 2032. Siemens Energy's latest steam turbine order from Babcock & Wilcox is reported at a 12-to-15-month delivery window, and a packaged boiler ships inside a year.
- A simple-cycle gas turbine burns about 10,975 Btu per kilowatt hour; a combined-cycle block burns 7,535. Same fuel, about 45 percent more electricity, and 31 percent less carbon per megawatt hour for the air permit.
- Steam turbine orders for combined-cycle service doubled in 2025, and the very large frames are already backing up. The window that is open today for mid-sized units will not stay open.
- The steam side is not cheap to build. It is cheap to run, because it burns nothing, and it is the only part of a 2030 combined-cycle plant that can still be bought with a date.
- Simple cycle is being built for speed, with the steam cycle "added later." Later is a slot that may not exist.
- A used or unfired steam turbine that matches the exhaust of the gas turbines on site is worth more today than at any point in twenty years, and there are not many of them.
Why is the steam turbine suddenly in demand?
Because it is the one large rotating machine you can still get. GE Vernova said on its July call that a large gas turbine ordered now arrives around 2031, and by its October call it was taking reservations for 2032. Mitsubishi Power said on October 27 that its 2028 and 2029 slots are nearly full and new orders are "delivery at around 2031." Against that, the steam side looks like a different industry. Siemens Energy's August order from Babcock & Wilcox, twenty 50 MW steam turbine generators for its data center program, a second gigawatt on top of the Base Electron units, carries a 12-to-15-month delivery window according to Turbomachinery International. Those are small machines; nobody has published a quote for a 150 MW combined-cycle unit, and the honest reading of the order book below is that the window for larger frames is narrower than that. GE Vernova's own pitch for its steam turbines is that they can be "installed and operational in eight months or less," which is an installation claim rather than a quoted lead time, but no one has said that about a gas turbine since 2023. Rentech says it can build and ship a packaged boiler within a year of the order. "Boilers are built every day," is how Brandy Johnson, Babcock & Wilcox's chief technology officer, put it to Power Engineering.
Rentech Boiler Systems in POWER, September 2026; Siemens Energy delivery window on the Babcock & Wilcox order, Turbomachinery International, September 2026; GE Vernova July 22 and October 28, 2026 earnings calls; Mitsubishi Power, October 27, 2026. Timeline runs from an order placed in November 2026.
The reason the two halves of a power plant are on different clocks is manufacturing, not demand. A heavy-frame gas turbine lives on single-crystal castings for its hot section, and the handful of foundries that pour them are the bottleneck the whole industry is queued behind. A steam turbine is forgings, blades and a casing, built by a wider field of shops on a supply chain that peaked near 140 GW a year in 2015 and ran below 50 GW in 2019. There is slack in it. POWER's Drew Robb estimates about 50 GW of spare capacity. That slack is what Cummins bought.
It is being used up. Steam turbine unit orders rose 10 percent in 2025, to 588 machines. Orders for combined-cycle service roughly doubled, with capacity up 128 percent, and combined cycle went from under 11 percent of unit orders to 19.4 percent, because every gas turbine slot that was signed through the back half of the decade pulled a steam turbine behind it. Siemens Energy alone booked 132 units. Robb's warning is the one that matters: in a couple of years, steam turbine backlogs may stretch as far as the gas turbine ones. For the largest frames, above 300 MW for the combined-cycle buildout and above a gigawatt for the nuclear restarts, that is already happening.
What does a steam turbine add to a simple-cycle plant?
Roughly half again as much power from the gas you are already burning. A gas turbine turns 35 to 40 percent of its fuel into electricity. The rest leaves the exhaust at around 1,000 degrees Fahrenheit. A heat recovery steam generator, which is a boiler with no burner, captures that heat as steam, and a steam turbine turns the steam into a second block of electricity with no additional fuel. That is all a combined-cycle plant is. In a typical two-on-one F-class block, the steam turbine is about a third of the output.
U.S. Energy Information Administration, Electric Power Annual, table 8.2, 2025 values. Tested heat rates at full load.
The EIA's 2025 numbers put a simple-cycle gas turbine at 10,975 Btu per kilowatt hour and a combined-cycle plant at 7,535. Hold the fuel constant and the combined-cycle block makes about 45 percent more electricity. A 300 MW simple-cycle campus becomes roughly 435 MW, and the extra 135 MW costs nothing to run. Price it instead: at $3.50 gas, simple cycle burns about $38 of fuel per megawatt hour and combined cycle about $26, which on 300 MW at a 90 percent capacity factor is roughly $28 million a year, every year, for the life of the plant. The boiler-and-steam-turbine route Applied Digital took sits at 10,293, which is why it plans to convert its sites to combined cycle once gas turbines arrive and keep the boilers for supplementary steam. The steam turbine it buys in 2026 is still the steam turbine in its 2031 plant.
Carbon follows fuel. A combined-cycle megawatt hour carries 31 percent less CO2 than a simple-cycle one, and the same proportion of everything else that comes out of a stack. That is not an ESG point. It is a permitting point. Nebius has been struggling to get an air permit for a 400 MW onsite plant in New Jersey. Every ton of emissions per megawatt hour is a ton the state's air office is counting against the site, and a bottoming cycle cuts the count by nearly a third without touching the gas turbines.
Why is nobody building it that way?
Because the industry has organized itself around first power, and first power is a gas turbine problem. Stargate Abilene is 39 LM2500XPRESS units in simple cycle. Pacifico Energy's eight Ansaldo AE64.3A frames for its West Texas campus are 624 MW "before the addition of any steam cycle." At the PROENERGY conference in January, John Adams of Crusoe, the power developer for Stargate, said simple cycles are being built now for speed and "combined cycles will be added later." The order book says the same thing: 90 percent of the steam turbine megawatts ordered in 2025 were in units above 150 MW, the big utility blocks like Homer City, seven 7HA.02 machines and seven steam turbines from day one, not the 100-to-300 MW campuses being stood up behind the meter.
The objections are real, and worth stating plainly. A steam cycle is slower to build than the gas turbines it sits behind: the HRSG, the condenser, the steam piping and the water treatment are a second construction program, and a bottoming cycle on a running plant is a year and a half of work at least. A steam turbine wants to run steady, and AI load swings several times a second; the answer is the one Oracle's Ram Nagappan gave Power Engineering, a battery in front of the plant to absorb the swings, so the gas turbines and the batteries do the moving and the steam turbine carries the base. Cooling needs water or an air-cooled condenser, and an air-cooled condenser costs a few points of efficiency in a Texas summer. And the capital is not free.
And it is real capital. What it buys is a megawatt with no fuel bill and a delivery date. Set it against the alternative, which is a third gas turbine. A developer who needs 435 MW on a site in 2028 can order three gas turbines for 2031 or two gas turbines and a steam turbine for 2028, and the steam turbine's megawatts cost $26 an hour less to run than the third turbine's, forever. Put that way the decision makes itself, and the only reason it is not being made is that the steam turbine is not the thing anyone is panicking about yet. The Applied Digital order says the panic is coming. The 2025 order book says the big frames are already gone.
Where does a steam turbine come from in 2027?
Three places, and the first is closing. An OEM order for a mid-sized combined-cycle steam turbine is still quoted in months rather than years, and that holds for as long as the spare capacity in the supply chain holds. The 2025 numbers say it is being drawn down fast, from the top of the size range downward. A developer who wants an OEM slot for a 100-to-250 MW steam turbine should take it this year, not next.
The second is the secondary market, and it is thinner than the gas turbine side. Retiring coal plants are full of steam turbines, but a coal unit's turbine was built for a fired boiler's steam conditions, and it is rarely a clean fit behind a heat recovery steam generator. The units that matter are the ones built for a combined-cycle block and never run: stranded projects, cancelled plants, equipment that sat in crates. When Hallador paid $350 million for Energy World's unfired Siemens equipment at Pagbilao, the package included a steam turbine, and that is not incidental. The gas turbines gave Hallador its Merom simple-cycle project. The steam turbine is what lets it be a combined-cycle plant without a 2032 slot.
The third is a used unit through a shop, opened, inspected, soft parts replaced and re-warranted, which is the same path used gas turbines take and is priced the same way: against the new-build cost, the new-build date and what the site makes in the gap.
What all three have in common is that the thing being bought is a match. A steam turbine is sized to the steam its gas turbines can raise: one F-class machine, two E-class, four 6B frames, three SGT-800s, each pairing raises a particular quantity of steam at particular conditions, and a steam turbine designed for that duty is worth far more to that site than a larger or smaller one would be. The buyer's first question is not the price. It is whether the steam conditions match the exhaust on site, and whether the unit is 60 Hz.
What this means
For the next five years, the steam turbine is the cheapest firm megawatt in the United States, because it is the only one that comes with its fuel already paid for and a delivery date inside the decade. The developers building simple cycle today are building half a plant and calling the other half "later." Later is a steam turbine slot, and the order book says those are being taken.
A site that owns its gas turbines and has not bought the steam turbine is leaving a third of its plant in the exhaust stack. Buying it now, new or unfired or used, is far cheaper to run than the gas turbine it replaces, arrives years sooner, and is the one procurement decision that gets easier to regret every quarter. Genloop holds an unused 160 MW Alstom reheat steam turbine generator, never fired, 60 Hz, sized for combined cycle behind a 7F, two 7E, two 6FA, four 6B or three SGT-800 machines. It is on the register and can ship now.